Challenge
Design, supply and install a turnkey solution for abatement system for pollutants from operation of two copper and brass furnaces, in Algeria. The system is to protect filters against high temperature & flames.
Solution
One extraction, gas filtration system which included a monitoring & control over temperature, also flame/spark arrestors, has been designed, discussed with the customer’s operators in Algeria and executed accordingly.
The total capacity of 35,000 m3 gas flow was handled through three identical parallel modules, each contents Hammam bag house filter PJF-1215, Hammam cyclone HEC-100-sbut one extraction 75kW fan with speed control. This arrangement targeted energy saving by permitting a partial operation.
Result
Hammam work scope completed and accepted by the client.